In Scrum, Team Velocity is a good metric to track the progress of product development. a) Yes b) No

Author: Avinash Upadhyay



Answer:

B) No In Scrum, the real mark of progress is the delivery of a useable product Increment (thereby bringing the product closer to the overall Product Goal) in every Sprint. Correct answer is ‘b'