Question:

Select all that apply. Before starting the first Sprint, what needs to be in place? a) A complete Product Backlog capturing detailed product needs. b) Availability of the Project Manager. c) Just enough Product Backlog Items with business ideas for the first Sprint. d) Completed System Architecture. e) Staffed Scrum Team.

Author: Avinash Upadhyay



Answer:

C) Just enough Product Backlog Items with business ideas for the first Sprint. e) Staffed Scrum Team. There are no preconditions for the first Sprint. The availability of a Scrum Team and a list of business ideas for the first Sprint are enough to start the Sprint. Correct answers are ‘c’ and ‘e.’