SEARCH
You are in browse mode. You must login to use MEMORY

   Log in to start


From course:

Chapter 1 - A new approach for complex problems

» Start this Course
(Practice similar questions for free)
Question:

Sprint Backlog MUST contain at least one improvement item (identified from the Sprint Retrospective) a) True. b) False.

Author: Avinash Upadhyay



Answer:

B) False. In Sprint Retrospective, the Scrum Team identifies the most helpful changes (in is way of working) to improve its effectiveness. The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint, but it is not mandatory. Correct answer is ‘b.’


0 / 5  (0 ratings)

1 answer(s) in total