Question:

During the Sprint, while the Sprint Backlog can be modified as more is learned, no changes are made that would endanger the Sprint Goal. a) True b) False

Author: Avinash Upadhyay



Answer:

A) True If the Sprint Goal is endangered, it would lead to cancellation of the Sprint. Correct answer is ‘a.’