Question:

Within every Sprint, the working Increment should be tested progressively starting from unit testing, then integration testing, and finally user acceptance testing. a) Yes. It is the prescribed method. b) No. The test strategy is decided by the Quality Assurance Lead in the team. c) Not necessarily. It is up to the team to find the best approach to testing. d) Incorrect. It should also include non-functional testing.

Author: Avinash Upadhyay



Answer:

C) Not necessarily. It is up to the team to find the best approach to testing. While the team needs to ensure that each Increment is thoroughly tested, all Increments work together and meet the Definition of Done, it is up to the team to find the best approach to achieve this. Correct answer is ‘c.’