SEARCH
You are in browse mode. You must login to use MEMORY

   Log in to start


From course:

Chapter 1 - A new approach for complex problems

» Start this Course
(Practice similar questions for free)
Question:

The difference between the Product Burn Down chart & the Sprint Burn down chart is a) In the Product Burn Down chart, the number of Product Backlog items is shown on the Y axis. In the Sprint Burn Down chart the number of tasks is shown on the Y axis. b) In the Product Burn down chart, the sprints are shown on the X axis. In the Sprint Burn Down Chart, the days of the sprint are shown in X Axis. c) In the Product Burn-down Chart, the Sprints are shown on the y-axis.In the Sprint Burn-down Chart, the days are shown on the y-axis.

Author: Avinash Upadhyay



Answer:

B) In the Product Burn down chart, the sprints are shown on the X axis. In the Sprint Burn Down Chart, the days of the sprint are shown in X Axis For both Product Burn Down chart & Sprint Burn Down chart, the Y axis represents the work remaining. Note that the number of work items (tasks) is different from the "amount of work". Correct is b


0 / 5  (0 ratings)

1 answer(s) in total