Question:

A discussion of what to do next is an additional event in the Sprint Review. a) False b) True, and the Scope of the Next sprint is also finalized c) True, It may capture probable Backlog items for the next sprint, but the scope of the Next sprint is deferred until next sprint planning.

Author: Avinash Upadhyay



Answer:

Every Scrum event is an opportunity for inspection and adoption. In the Sprint Review, inspecting the Product increment provides insights and clarity. This newly found knowledge is used to "adopt the next steps" i.e find out what to do next. Correct answer is "c"