Question:

Given a complex product and its relevance to multiple departments, a Scrum team expects that they need to invite many stakeholders for the sprint Review. It estimates that review will take more than four hours. The Scrum team can increase the Sprint Review Duration. a) True b) False

Author: Avinash Upadhyay



Answer:

-----Answer--- b) False Every Scrum event is Time boxed to reduce risk and eliminate waste. If there are valid reasons that require more time, it might be due to reasons such as added complexity. The team needs to address these root causes and the time Box should be followed to contain risks. Correct answer is "b. More Example of where Time Box is likely to be broken but should be safeguarded are  A daily scrum cannot exceed 15 minutes even if the team size is increased.   A sprint cannot go beyond one month even if there are almost done and may just need few more days to be completely done.


0 / 5  (0 ratings)

1 answer(s) in total